| Before You Build
|

Below is a timetable of what to expect when it's time to build. Please note that these are only estimates.
1) Site Plan:
After all necessary permits have been obtained, you will now turn to your site plan to mark where your house will be built on your land. This is done with the help of the site plan and your contractor.
Time frame: this can be completed within about 2 hours.
2) Excavation and Groundbreaking:
Clearing of the land ensures that enough space is available for tractors and forklifts to operate during construction. At this time, your driveway may also be cleared to allow access for deliveries. The excavator will also dig out for the foundation and basement (if applicable) and this is typically done after the land has been cleared and within the same time frame as the excavation.
Time frame: 1 to 7 days.
3) Delivery of Panel Package:
BuildandSave.com will arrange a time and day for your panel package to be delivered to the job site.
Time frame: 1 day.
4) Utilities:
The sub-contractors will need water and temporary electrical service installed. If you've chosen a well or septic system, check with your sub-contractor to see if this is the time to have them installed.
Time frame: 1 day.
5) Footers:
Your concrete sub-contractor will pour your footers according to your plans and specs. After this stage, an inspector may be required to inspect and check the footers to ensure they meet with township or county building codes.
Time frame: 1 to 2 days.
6) Foundation:
Your home can be built on almost any type of foundation: brick, block, concrete, pre-cast or all-weather wood. Your masonry sub-contractor will construct your foundation as specified in your plans and specifications. Your foundation may include a full basement or concrete slab (if using a concrete slab, all plumbing rough-ins must be complete before pouring your slabs).
Time frame: 1 to 2 weeks, depending on foundation type and sub-contractor.
7) Frame Construction:
Your general contractor or sub-contractor will erect your panel package. Once your shell is intact, "drying-in" will occur (the process of protecting your home from weather). This doesn't always mean that your roof is completed and if you're building a chimney, this needs to be erected before the roof can be completed.
Time frame: 1 to 3 weeks.
8) Chimney and Fireplace:
Prior to completion of the roof, all fireplaces and chimneys should be installed and completed. This allows proper flashing to be installed around the chimney.
Time frame: 1 to 7 days.
9) Roofing:
The roof shingles will be installed unless this occurred at the "drying-in stage" (no chimneys were erected). All exterior trim including fascia, soft and gable ends should be completed at this time.
Time frame: 1 to 3 days.
10) Drywall:
Prior to having your drywall hung, all plumbing, electrical, heating and air conditioning should be roughed-in by your sub-contractors. Depending on your plans and specs some of this may have been completed as the framing was being constructed. After any necessary roughing-in, the drywall is hung.
Time frame: up to 2 weeks depending on the number of rooms and the sub-contractor.
11) Interior Trim Painting/Staining:
Doors, molding, cabinets, etc., are installed. After all trim is in place, painting and staining is performed (if not pre-painted or pre-stained). During this stage any outside painting or staining is also completed. If you choose not to paint or stain the outside of your home, you can treat the wood now or let it age naturally.
Time frame: Up to 4 weeks, depending on amount of painting or staining.
12) Kitchen and Bathroom(s):
All counter tops and flooring must be complete so that plumbing can be finished. Any entry ways or foyers that are of the same flooring substance are also completed at this time (except carpeting).
Time frame: Up to 2 weeks.
13) Timing Out:
Plumbing, electrical, heating air-conditioning and wall/baseboard plates are completed. The plumber installs the bathroom(s) and kitchen fixtures. The electrician will install all switches, outlet covers and wires for all appliances.
Time frame: These combined processes can take up to 5 days.
14) Flooring:
Hardwood floors are finished. After completing any hardwood flooring the carpeting and padding is installed.
Time frame: Up to 4 days, depending on the number of rooms.
15) Driveway and Walkways:
To prevent any damage, you may want to wait to start this stage until all construction equipment has been removed.
Time frame: Up to 4 days.
16) Landscaping:
Depending on the time of year your home is constructed you may need to wait to complete this stage.
Time frame: Up to 4 days, depending on the size of your lot.
|
|
|
|
|
|